Projects
Project ID
15.04, ARKnet Deployment
Summary
Funded, Approved May 2015.
First Sector Site deployed 27 Feb 2016 to Lehigh Permanente Cement Plant. Four client sites are planned through the rest of the
Fiscal year.
Background
ARKnet is the first step toward building a Wireless Emergency Intranet for Cupertino that will support our emergency responders with a backup high speed data network.
Plan
Milestone | Date | Status |
Requirements Complete | 31 May 2015 | Complete |
Design Complete | 30 Dec 2015 | Complete |
Lehigh Sector Deployment | 27 Feb 2016 | Complete |
EOC client rollout | TBD | Planned |
Service Center rollout | TBD | Planned |
Portable Field Station rollout | TBD | Planned |
Cpertino Fire Station rollout | TBD | Planned |
References
Product Data Sheet, May 2015
Functional Requirements Document, January 2016
System Design Document, January 2016
Lehigh Sector Site Install Pictures, February 2016
Status Reports
150819,
151021,
160201
Other Notes
Upcoming Activities
4 Mar 2021, General Meeting
CuSD System Overview. 7:30pm to 9:00pm, Teleconference
1 Apr 2021, General Meeting
SJW System Overview. 7:30pm to 9:00pm, Teleconference
6 May 2021, General Meeting
ISA Exercise Prep. 7:30pm to 9:00pm, Teleconference
15 May 2021, ISA Field Comm Exercise
8:00am to 12:00pm, Details to follow
3 Jun 2021, General Meeting
Field Day Prep; 4th of July Prep(?). 7:30pm to 9:00pm, Teleconference